Installation, starting and adjustment of ventilation and air conditioning systems A Guide. Alexey Vasilyevich Antipov

Installation, starting and adjustment of ventilation and air conditioning systems A Guide - Alexey Vasilyevich Antipov


Скачать книгу
by continuous roller running-in, without damaging the surface and coating. Automatic feed control guarantees seam accuracy and uniform joint density. TRUMPF folding machines are suitable for both straight boxes and bends, with a minimum internal radius of only 300 mm.

      To install grilles, blinds, valves and air conditioners themselves, it is often necessary to make cutouts in an already mounted box. Especially for this application, TRUMPF has developed the C 160 slotted scissors, which allow you to make cutouts with great accuracy, without deforming the sheet, and the chips do not get inside the box, because they stand out above the surface of the sheet with a continuous tape. You can start and finish the cut at any point on the surface of the box; by turning the small handle on the cutting head, the chips are bitten off at the desired point. The edge of the cut is perfectly smooth. These scissors can be used to cut welded spiral seams on round ducts up to 2.5 mm thick.

      Questions to Chapter 6

      1. Name the composition of the joint team of locksmiths.

      2. Explain the principle of operation of the instrument from the main set (one, at the student's choice).

      3. Describe the method of connecting the flange to the end of the duct.

      4. What is the reason for the location of the connecting element relative to the duct?

      5. What are the advantages of a folding connection?

      Chapter VII. Installation of ventilation equipment

      The production of installation ventilation works at facilities implies preparation for the installation of ventilation equipment, which requires careful preparatory work. Special attention should be paid to the reality of the implementation of design solutions by the installation team, both technically and in terms of execution.

      7.1.Projects of production of works

      The project of work production is the basic guide for the organization and production of installation work at the facility. Project of work production helps to plan all the preparatory work, including the execution of orders for air ducts and applications for ventilation equipment and materials, to determine the storage locations of bulky ventilation parts. The project of work production contributes to the uninterrupted conduct of installation work, improving the quality of installation.

      The complete project of work includes the following sections:

      1) situational master plan, usually on a scale of 1:400, with reference to the storage locations of air ducts and ventilation equipment and an intra-building transport scheme;

      2) schematic plan of the object with drawing of axes and locations of ventilation equipment;

      3) list of ventilation equipment supplied by the customer;

      4) characteristics of air ducts for ventilation systems and a list of installation drawings or sketches on them;

      5) schedule of receipt of ventilation blanks (ducts and standard ventilation parts) to the facility;

      6) the schedule of receipt of ventilation equipment, agreed with the customer;

      7) calendar (network) schedule of work with deadlines for the delivery of the object;

      8) statement of basic and auxiliary materials;

      9) instructions on methods and methods of installation work and safety;

      10) a statement of the necessary mechanisms, tools and means of small mechanization specifically for the object;

      11) production calculations and summary statements of labor costs and wages;

      12) the schedule of the need for workers.

      In the calendar (network) schedule of work, the deadlines for preparing the object or individual premises for installation, the deadlines for the completion of construction work in ventilation chambers, the deadlines for the supply of electricity to ventilation equipment and hot water to heaters and, most importantly, the deadlines for the installation of ventilation systems should be determined. A schedule for the delivery of ventilation equipment to the facility must be agreed with the customer's organization in advance.

      For objects with a small amount of ventilation work and capital repairs, abbreviated The project of work production is the basic guide for the organization and production of installation work at the facility. Project of work production helps to plan all the preparatory work, including the execution of orders for air ducts and applications for ventilation equipment and materials, to determine the storage locations of bulky ventilation parts. The project of work production contributes to the uninterrupted conduct of installation work, improving the quality of installation.

      7.2. Acceptance of the object for installation work

      Prior to the start of installation work on the object or on its part, a list of individual types of construction works, the performance of which is necessary for the subsequent installation of ventilation systems, and the timing of their execution must be agreed between the representatives of the installation organization and the general contractor.

      Such works include:

      1) installation of foundations, platforms and other supporting structures for ventilation equipment;

      2) installation of walls and partitions in ventilation chambers, as well as ceilings, if the project of work production does not provide for the supply of ventilation equipment through the top of the chambers;

      3) installation of embedded parts provided for by the project in ventilation chambers for connecting ventilation equipment and along the route of systems for fixing air ducts;

      4) installation of horizontal and vertical mounting openings for the supply of ventilation equipment and ducts from an on-site warehouse to the place of their installation;

      5) installation of walls and ceilings in the places of laying air ducts;

      6) plastering and painting of walls, ceilings and partitions in the places of laying air ducts and installing air distributors;

      7) punching holes in places where air ducts pass through walls, ceilings and partitions, if they are not left during the construction of the building;

      8) installation of reinforced concrete cups on floors in places of passage of ventilation shafts and installation of roof fans;

      9) the device of fasteners for large-sized air ducts and platforms for cyclones, scrubbers, filters, etc.;

      10) the device of ventilation ducts in construction (brick, concrete);

      11) glazing of window openings and lanterns

      12) cleaning of ventilation work sites from construction debris.

      After performing these works on the entire object, the object is accepted under a bilateral act for installation. It is especially necessary to carefully prepare the rooms of the ventilation chambers, where all construction work (except clean floors and final painting) must be carried out and the lifting devices provided for by the project for the operation and repair of ventilation equipment must be installed. For the passage of air ducts through building structures, the holes in them must be 150 mm larger than the diameter of a round or the dimensions of the sides of a rectangular air duct.

      By the time the installation works begin, the general contractor must provide the installation team with:

      a) cabins for workers, a room for a workshop and a storeroom, open storage areas and sheds for storing air ducts, ventilation equipment and products in the area of operation of vehicles;

      b) supply of electricity, water and heat during the cold period for the production of works and for domestic premises;

      c) vertical and horizontal on-site transport;

      d) electric lighting in places where ventilation works are performed;

      e) fire and guard protection.

      To perform installation work directly on the site, it is necessary to have the following technical documentation:

      1) two copies of working drawings;

      2)