      (4) Heating shall be installed so as to be capable of maintaining a room temperature of 70 degrees Fahrenheit at a point three feet above the floor in any living space if the heating was installed pursuant to a building permit application submitted prior to January 1, 2008, or capable of maintaining a room temperature of 68 degrees Fahrenheit at a point three feet above the floor and two feet from exterior walls in all habitable rooms at the design temperature if the heating was installed pursuant to a building permit application submitted on or before January 1, 2008.

      (5) Living space air-conditioning, if any, shall be provided in a manner consistent with the size and efficiency design criteria specified in Title 24 of the California Code of Regulations or its successor.

      (6) Attached structures shall be constructed to comply with interunit noise transmission standards set by the applicable government building codes, ordinances, or regulations in effect at the time of the original construction. If there is no applicable code, ordinance, or regulation, this paragraph does not apply. However, no action shall be brought pursuant to this paragraph more than one year from the original occupancy of the adjacent unit.

      (7) Irrigation systems and drainage shall operate properly so as not to damage landscaping or other external improvements. However, no action shall be brought pursuant to this paragraph more than one year from close of escrow.

      (8) Untreated wood posts shall not be installed in contact with soil so as to cause unreasonable decay to the wood based upon the finish grade at the time of original construction. However, no action shall be brought pursuant to this paragraph more than two years from close of escrow.

      (9) Untreated steel fences and adjacent components shall be installed so as to prevent unreasonable corrosion. However, no action shall be brought pursuant to this paragraph more than four years from close of escrow.

      (10) Paint and stains shall be applied in such a manner so as not to cause deterioration of the building surfaces for the length of time specified by the paint or stain manufacturers’ representations, if any. However, no action shall be brought pursuant to this paragraph more than five years from close of escrow.

      (11) Roofing materials shall be installed so as to avoid materials falling from the roof.

      (12) The landscaping systems shall be installed in such a manner so as to survive for not less than one year. However, no action shall be brought pursuant to this paragraph more than two years from close of escrow.

      (13) Ceramic tile and tile backing shall be installed in such a manner that the tile does not detach.

      (14) Dryer ducts shall be installed and terminated pursuant to manufacturer installation requirements. However, no action shall be brought pursuant to this paragraph more than two years from close of escrow.

      (15) Structures shall be constructed in such a manner so as not to impair the occupants’ safety because they contain public health hazards as determined by a duly authorized public health official, health agency, or governmental entity having jurisdiction. This paragraph does not limit recovery for any damages caused by a violation of any other paragraph of this section on the grounds that the damages do not constitute a health hazard.

      (Amended by Stats. 2012, Ch. 770, Sec. 2. Effective January 1, 2013.)

      897. The standards set forth in this chapter are intended to address every function or component of a structure. To the extent that a function or component of a structure is not addressed by these standards, it shall be actionable if it causes damage.

      (Added by Stats. 2002, Ch. 722, Sec. 3. Effective January 1, 2003.)

      CHAPTER 3. Obligations [900 — 907]

      (Chapter 3 added by Stats. 2002, Ch. 722, Sec. 3.)

      900. As to fit and finish items, a builder shall provide a homebuyer with a minimum one-year express written limited warranty covering the fit and finish of the following building components. Except as otherwise provided by the standards specified in Chapter 2 (commencing with Section 896), this warranty shall cover the fit and finish of cabinets, mirrors, flooring, interior and exterior walls, countertops, paint finishes, and trim, but shall not apply to damage to those components caused by defects in other components governed by the other provisions of this title. Any fit and finish matters covered by this warranty are not subject to the provisions of this title. If a builder fails to provide the express warranty required by this section, the warranty for these items shall be for a period of one year.

      (Added by Stats. 2002, Ch. 722, Sec. 3. Effective January 1, 2003.)

      901. A builder may, but is not required to, offer greater protection or protection for longer time periods in its express contract with the homeowner than that set forth in Chapter 2 (commencing with Section 896). A builder may not limit the application of Chapter 2 (commencing with Section 896) or lower its protection through the express contract with the homeowner. This type of express contract constitutes an “enhanced protection agreement.”

      (Added by Stats. 2002, Ch. 722, Sec. 3. Effective January 1, 2003.)

      902. If a builder offers an enhanced protection agreement, the builder may choose to be subject to its own express contractual provisions in place of the provisions set forth in Chapter 2 (commencing with Section 896). If an enhanced protection agreement is in place, Chapter 2 (commencing with Section 896) no longer applies other than to set forth minimum provisions by which to judge the enforceability of the particular provisions of the enhanced protection agreement.

      (Added by Stats. 2002, Ch. 722, Sec. 3. Effective January 1, 2003.)

      903. If a builder offers an enhanced protection agreement in place of the provisions set forth in Chapter 2 (commencing with Section 896), the election to do so shall be made in writing with the homeowner no later than the close of escrow. The builder shall provide the homeowner with a complete copy of Chapter 2 (commencing with Section 896) and advise the homeowner that the builder has elected not to be subject to its provisions. If any provision of an enhanced protection agreement is later found to be unenforceable as not meeting the minimum standards of Chapter 2 (commencing with Section 896), a builder may use this chapter in lieu of those provisions found to be unenforceable.

      (Added by Stats. 2002, Ch. 722, Sec. 3. Effective January 1, 2003.)

      904. If a builder has elected to use an enhanced protection agreement, and a homeowner disputes that the particular provision or time periods of the enhanced protection agreement are not greater than, or equal to, the provisions of Chapter 2 (commencing with Section 896) as they apply to the particular deficiency alleged by the homeowner, the homeowner may seek to enforce the application of the standards set forth in this chapter as to those claimed deficiencies. If a homeowner seeks to enforce a particular standard in lieu of a provision of the enhanced protection agreement, the homeowner shall give the builder written notice of that intent at the time the homeowner files a notice of claim pursuant to Chapter 4 (commencing with Section 910).

      (Added by Stats. 2002, Ch. 722, Sec. 3. Effective January 1, 2003.)

      905. If a homeowner seeks to enforce Chapter 2 (commencing with Section 896), in lieu of the enhanced protection agreement in a subsequent litigation or other legal action, the builder shall have the right to have the matter bifurcated, and to have an immediately binding determination of his or her responsive pleading within 60 days after the filing of that pleading, but in no event after the commencement of discovery, as to the application of either Chapter 2 (commencing with Section 896) or the enhanced protection agreement as to the deficiencies claimed by the homeowner. If the builder fails to seek that determination in the timeframe specified, the builder waives the right to do so and the standards set forth in this title shall apply. As to any nonoriginal homeowner, that homeowner shall be deemed in privity for purposes of an enhanced protection agreement only to the extent that the builder has recorded the enhanced protection agreement on title or provided actual notice to the nonoriginal homeowner of the enhanced protection agreement. If the enhanced protection agreement is not recorded on title or no actual notice has been provided, the standards set forth in this title apply to any nonoriginal homeowners’ claims.