Demand Driven Material Requirements Planning (DDMRP), Version 2. Carol Ptak

Demand Driven Material Requirements Planning (DDMRP), Version 2 - Carol Ptak


Скачать книгу
6-1 Product structures for FPE and FPF

      Cumulative lead time (CLT): The longest planned length of time to accomplish the activity in question. It is found by reviewing the lead time for each bill of material path below the item; whichever path adds up to the greatest number defines cumulative lead time. (p. 38)

      Purchasing lead time (PLT): The total lead time required to obtain a purchased item. Included here are order preparation and release time; supplier lead time; transportation time; and receiving, inspection, and put-away time. (p. 142)

      Considering these definitions, for FPE the manufacturing lead time is 2 days, while the cumulative lead time is 26 days (20-day purchasing lead time + 4 days manufacturing lead time for 101 + 2 days manufacturing lead time for FPE). In the case of FPF, the manufacturing lead time is 3 days, while the cumulative lead time is 27 (20-day purchasing lead time + 4 days manufacturing lead time for 101 + 3 days manufacturing lead time for FPF).

      To properly apply the six factors, we will need additional information about the environment. Figure 6-2 shows the product and routing structure of both FPE and FPF together. A “routing,” as defined by APICS, is “information detailing the method of manufacture of a particular item. It includes the operations to be performed, their sequence, the various work centers involved, and the standards for setup and run.” Together, the BOM and the routing paint a relatively complete picture of the view needed to consider positioning for this scenario. Note that no run rates and setup times have been defined, as these will not be relevant for this simple example.

      Once a part 205P is introduced to the manufacturing process, it is run through a series of resources (A > B > C > D) and combined with a converted 204P at resource Z. Part 204P is run through a series of resources (B > C > E > F). Resource Z is an assembly operation and the final step in producing intermediate part 101. This conversion process (from 204P and 205P to 101), assuming concurrent activity across paths, takes four days on average. Thus 101’s manufacturing lead time is four days.

img

      Resource Z is a “convergent point.” A convergent point is any place where routing legs come together. As discussed in Chapter 3, these points of integration occur most often where significant delays accumulate because all parts must be present for the resource to perform its operation. Resource Z requires a converted 204P from resource F and a converted 205P from resource D at the same time and quantity. This make resource Z a candidate for a resource that we would like to protect as much as possible—a critical operation.

      Part 101 is a “point of divergence.” A divergent point means that part 101 can be directed into different manufacturing paths culminating in various end items. A divergent point represents a commitment that cannot be practically or cost-effectively reversed. An example would be the introduction of a sheet of steel into a fabrication process. Once the sheet is cut, the options available to use it are narrowed significantly. Thus the decision to cut it precludes it from being used in many other ways.

      For this example, part 101 is directed to resources S and T to either begin the process to convert it to FPE or be combined with the purchased part 102P to be finished into an FPF. The conversion into FPE takes two days, and the conversion to FPF, a more complicated build, takes three days. Thus the manufacturing lead time is two days for FPE and three days for FPF.

      When checking with sales and customer service, we find that the customer tolerance time for both products is at three days. FPF has lower volumes, as it is a higher-end product, but the market expects it within the same time frame as the lower-end product FPE. Additionally, sales has indicated that there are frequent opportunities in the market for FPE to win quick-turn business. Customers are not inclined to pay more for the items, but the volume would definitely increase with the capability to offer same-day fulfillment. Finally, with the exception of quickturn requests, this company typically receives sales orders at least three days in advance for both products. Occasionally there can be large orders, but those larger orders tend to have at least two weeks of sales order visibility.

      When checking with purchasing, we discover that the suppliers for 204P and 205P have decent reliability. Occasional disruptions do happen, but overall both have performed well over the last year. The supplier for 102P, however, is a different story. This supplier is notorious for late deliveries and even routinely produces suspect quality. Figure 6-3 summarizes the positioning criteria information for this example.

img

      Based on these answers, how should decoupling point positioning be approached in this environment? The impact of each of the criteria on the model is considered:

      

Customer tolerance time. Three days makes it a requirement to consider decoupling at the end item or 101 and 102P levels. To do anything less will require making product to some sort of anticipated signal or forecast and incur the negatives associated with that.

      

Market potential lead time. The opportunity for FPE suggests a benefit for decoupling and stocking at FPE. The additional volume or customers could provide profitable revenue growth.

      

Sale order visibility horizon. Decoupling at the finished goods or 101 and 102P levels would allow the environment to pace to actual sales orders. This is the most relevant demand signal assuring the alignment of our resources to actual requirements.

      

External variability. Demand variability does not seem to be a huge issue—large orders are typically known in advance. Supply variability is an issue for 102P. Stocking at 102P would seem prudent.

      

Inventory leverage and flexibility. Decoupling and stocking at 101 would allow the common component to flow to the end items as required.

      

Critical operation protection. While the suppliers for 204P and 205P are reliable, decoupling those positions would provide as much protection to resource Z as possible from a product structure perspective.

      In consideration of these answers to the positioning criteria, Figure 6-4 shows a model for this environment.

img

      The key elements and benefits of this model include:

      

The FPE stock position allows for quick-turn business to be satisfied. This allows for an increase in sales revenue.

      

The FPE stock position is minimized due to the short lead time from the decoupling point at 101.

      Скачать книгу