Cost Plus A Complete Guide - 2020 Edition. Gerardus Blokdyk

Cost Plus A Complete Guide - 2020 Edition - Gerardus Blokdyk


Скачать книгу
completed Cost Plus Scorecard will give you a clear presentation of which Cost Plus areas need attention.

      Cost Plus

      Scorecard Example

      Example of how the finalized Scorecard can look like:

      Cost Plus

      Scorecard

      Your Scores:

      BEGINNING OF THE

      SELF-ASSESSMENT:

      Table of Contents

      About The Art of Service7

      Included Resources - how to access7

      Purpose of this Self-Assessment9

      How to use the Self-Assessment10

      Cost Plus

      Scorecard Example12

      Cost Plus

      Scorecard13

      BEGINNING OF THE

      SELF-ASSESSMENT:14

      CRITERION #1: RECOGNIZE15

      CRITERION #2: DEFINE:27

      CRITERION #3: MEASURE:42

      CRITERION #4: ANALYZE:57

      CRITERION #5: IMPROVE:73

      CRITERION #6: CONTROL:88

      CRITERION #7: SUSTAIN:99

      Cost Plus and Managing Projects, Criteria for Project Managers:124

      1.0 Initiating Process Group: Cost Plus125

      1.1 Project Charter: Cost Plus127

      1.2 Stakeholder Register: Cost Plus129

      1.3 Stakeholder Analysis Matrix: Cost Plus130

      2.0 Planning Process Group: Cost Plus132

      2.1 Project Management Plan: Cost Plus134

      2.2 Scope Management Plan: Cost Plus136

      2.3 Requirements Management Plan: Cost Plus138

      2.4 Requirements Documentation: Cost Plus141

      2.5 Requirements Traceability Matrix: Cost Plus143

      2.6 Project Scope Statement: Cost Plus145

      2.7 Assumption and Constraint Log: Cost Plus147

      2.8 Work Breakdown Structure: Cost Plus149

      2.9 WBS Dictionary: Cost Plus151

      2.10 Schedule Management Plan: Cost Plus153

      2.11 Activity List: Cost Plus155

      2.12 Activity Attributes: Cost Plus157

      2.13 Milestone List: Cost Plus159

      2.14 Network Diagram: Cost Plus161

      2.15 Activity Resource Requirements: Cost Plus163

      2.16 Resource Breakdown Structure: Cost Plus164

      2.17 Activity Duration Estimates: Cost Plus166

      2.18 Duration Estimating Worksheet: Cost Plus168

      2.19 Project Schedule: Cost Plus170

      2.20 Cost Management Plan: Cost Plus172

      2.21 Activity Cost Estimates: Cost Plus174

      2.22 Cost Estimating Worksheet: Cost Plus176

      2.23 Cost Baseline: Cost Plus178

      2.24 Quality Management Plan: Cost Plus180

      2.25 Quality Metrics: Cost Plus182

      2.26 Process Improvement Plan: Cost Plus184

      2.27 Responsibility Assignment Matrix: Cost Plus186

      2.28 Roles and Responsibilities: Cost Plus188

      2.29 Human Resource Management Plan: Cost Plus190

      2.30 Communications Management Plan: Cost Plus192

      2.31 Risk Management Plan: Cost Plus194

      2.32 Risk Register: Cost Plus196

      2.33 Probability and Impact Assessment: Cost Plus198

      2.34 Probability and Impact Matrix: Cost Plus200

      2.35 Risk Data Sheet: Cost Plus202

      2.36 Procurement Management Plan: Cost Plus204

      2.37 Source Selection Criteria: Cost Plus206

      2.38 Stakeholder Management Plan: Cost Plus208

      2.39 Change Management Plan: Cost Plus210

      3.0 Executing Process Group: Cost Plus212

      3.1 Team Member Status Report: Cost Plus214

      3.2 Change Request: Cost Plus216

      3.3 Change Log: Cost Plus218

      3.4 Decision Log: Cost Plus220

      3.5 Quality Audit: Cost Plus222

      3.6 Team Directory: Cost Plus225

      3.7 Team Operating Agreement: Cost Plus227

      3.8 Team Performance Assessment: Cost Plus229

      3.9 Team Member Performance Assessment: Cost Plus231

      3.10 Issue Log: Cost Plus233

      4.0 Monitoring and Controlling Process Group: Cost Plus235

      4.1 Project Performance Report: Cost Plus237

      4.2 Variance Analysis: Cost Plus239

      4.3 Earned Value Status: Cost Plus241

      4.4 Risk Audit: Cost Plus243

      4.5 Contractor Status Report: Cost Plus245

      4.6 Formal Acceptance: Cost Plus247

      5.0 Closing Process Group: Cost Plus249

      5.1 Procurement Audit: Cost Plus251

      5.2 Contract Close-Out: Cost Plus254

      5.3 Project or Phase Close-Out: Cost Plus256

      5.4 Lessons Learned: Cost Plus258

      Index260

      CRITERION #1: RECOGNIZE

      INTENT: Be aware of the need for change. Recognize that there is an unfavorable variation, problem or symptom.

      In my belief, the answer to this question is clearly defined:

      5 Strongly Agree

      4 Agree

      3 Neutral

      2 Disagree

      1 Strongly Disagree

      1. Whom do you really need or want to serve?

      <--- Score

      2. Is it clear when you think of the day ahead of you what activities and tasks you need to complete?

      <--- Score

      3. What else needs to be measured?

      <--- Score

      4. Where do you need to exercise leadership?

      <--- Score

      5. Are controls defined to recognize and contain problems?

      <--- Score

      6. What extra resources will you need?

      <--- Score

      7. What is the extent or complexity


Скачать книгу