Practical Power Plant Engineering. Zark Bedalov

Practical Power Plant Engineering - Zark Bedalov


Скачать книгу
Illustration of safety Interlocks are hard wired into the electrical circuits

      The wiring tabulations, mentioned earlier, are generally not being updated. The schematics are updated in red and issued “As Built.” The commissioning approach, though relatively cumbersome, avoids all the simulations to be done and saves the time as the work is concentrated on fixing faulty wiring and wrong logic lines only, and not on all the wiring and all the logic. This approach may work providing the unit was being fully tested under all the operating conditions of loading, ramping, and stopping to expose the functioning of all the instrumentation, the transmitters, and indicating instruments. The transmitters may work correctly for certain loading and operating sequences, but rapid changes in the load may expose their weaknesses.

      In my judgment, the following are typical commissioning problems:

      1 Mechanical: Rare. They tend to be visible, but take longer (days) to fix and replace with spare parts if available.

      2 Electrical wiring: Due to wrong wiring, wrong schematics, inappropriate contact seating. This is diagnosed by going over the schematics and fixed within hours.

      3 Control logic software errors. This is diagnosed and modified within hours. Often, several attempts are tried.

      4 Nonresponsive devices (level switches, analogs, pressure switches, transmitters, etc.). The devices may be faulty or inappropriate for the application. These problems are relatively common and difficult to deal with because of their unpredictable and intermittent behavior. These issues may take several days to be discovered, repaired, and the fix confirmed when repaired.

      Naturally, all the changes implemented on Unit 1 in the wiring, control logic, and unresponsive field devices are immediately updated on the next unit if it is available, thus, insuring faster commissioning and release to operation.

      In an industrial plant, the commissioning is based on a system‐by‐system basis grinding, flotation, conveying, leaching, etc. Switchgear, transformers, MCCs, and motors are tested together under partially energized conditions. Each system is semiautonomous and gradually energized to prove it operates in proper sequence for starting and shutting down under specific conditions. The systems are being commissioned until the whole plant is made operational and ready for starting up from the control room and it is correctly represented on the control system monitors.

      Some say that commissioning is the slowest game in town. It is 90% logistics and preparation to position right people to the right places, keep them focused on the task with proper tools, and to prepare the safe environment and operating conditions for the test. The actual test may take only a few minutes to show a change in state on the instruments, or that something had moved or rotated. Conveyors start moving in sequence, grinders start grinding, and pumps start pumping and filling the tanks. Level switches regulate the speed of the drives to prove the set points established by the control system. The automation starts directing the process.

      For the commissioning to work well, one has to have a good cooperation of the mechanical, process, and controls engineers and excellent means of communications in the field. Why are the electrical engineers most often assigned to be the commissioning engineers? Well, I think because the electrical engineering is the hardest part of the project to understand. Electricity is the blood flow of the plant. It connects all the pieces in an invisible way that experienced electrical engineers can understand.

      During an RR, the owner's operators take over the plant operation in the presence of the suppliers in supervisory role. This is also a phase of practical training for the operators. The operators follow the directives of the dispatch center and load the machines accordingly in terms of MW and MVARs. The intent is to operate and expose the plant to all the operating modes and transitions without restrictions and as often as possible. As more and more automation and supervision is added to the plants the commissioning and RR tests get more and more involved.

      Each plant owner may dictate different constraints for RR. The rules may also depend on the unit performance during the commissioning. If the plant has been failing often, owners may impose more stringent conditions. In general, the unit must operate 30 days, 24 hours a day without a major failure that would cause the unit to reduce its capability to carry load. If that happens, the RR is restarted from the beginning. For instance, a failure of a pump with a successful automatic transition to the healthy pump will not be a cause to stop the RR, but considered a successful operating action.

      It is much easier to commission a plant if you had followed it through the design and construction into commissioning. Sometimes a commissioning engineer may be invited to do a commissioning on a plant that he/she may not be familiar with. There were a number of cases like this. One of difficult ones was in Lahore, Pakistan, where we were invited to conduct a commissioning and RR test after it has failed in 12 earlier attempts over a period of two years. It was a 5 × 30 MW thermal plant.

      During the RR, the plant was supposed to operate flawlessly for seven days without a single alarm while being tested under all the operating conditions. In addition, there was a specific test during the RR while all the plant units were running, called “Islanded Test.” An unexpected three‐phase fault is arranged on the HV line, connected to the plant. To pass the test, the plant had to separate itself from the grid, shutting down four units, while one unit was supposed to be left running and maintaining the plant station service load.

      Well, this time, it worked well, and the plant passed the test. We knew that this time, we had to take a different approach. We modified the protective relay settings and readjusted the governor transfer functions. Every short circuit is different, and the units are required to conform accordingly. Perhaps we were just plain lucky. It is hard to tell. This time the protective relays operated selectively and the new governor settings acted correctly.

       Load


Скачать книгу