dispatch following capability

       Reactive power dispatch follow

       Isochronous capability (droop)

       Dispatch MW ramp rate

       Fast ramp MW response

       Synchronous condenser mode switchovers

       Primary/secondary high‐frequency response

       Under‐frequency trip setting check (simulation)

       Loss of station service AC supply – switchover to standby power

       Black start, synchronizing on islanded grid dead bus

       House load operation on generator power for two hours

      Most commissioning engineers observe the testing in a passive way, and at the end of the test, they ask for the commissioning reports by the contractors. In their preprepared reports, you will never find a hick up or any failure noted. So, why bother having the reports, when everything is 100% perfect. In fact their reports are already done before they even start testing. Everything is Yes, Yes, OK, OK! There are tests that indeed go smoothly. Faults do happen and often due to multiple reasons that can be either fixed quickly or postponed and fixed later. That has to be recorded, as well as all the temporary deviations due to missing components, etc.

      We do our own commissioning or precommissioning report for reasons noted below. We do it directly on our PCs as the events evolve. We sit with the test engineers at the end of a large desk in front of the main control panel and observe and write:

       We do not make a story. We write the action.

       The testers pay more attention to their work in our presence. They cannot hide the actual facts.

       As active people, we can ask for repeat tests or test it from a different perspective or condition.

       Our report is chronological and timed as it happens. One never knows what and when something unusual will happen. It does happen and often. One wants to capture the moment and to include all the background details on what was in action before the occurrences of a failure.

       It includes the failures as a record, why and how they were resolved and made to be OK.

       Later on during the operation when something fails, one can look into the commissioning reports and figure out if this is a recurrence of the same fault and likely to be expected to happen again.

      1.4.1 Budget Estimate

      A typical project passes through a number of development phases, starting from an initial estimate, conceptual design for feasibility study, detailed design, construction, and start up.

      Let us name some typical projects:

       a power plant: hydro, diesel generation, gas combined cycle, etc., and

       an industrial project that may be an ore exploitation process, a factory of detergents, potato chips, and any other similar facility.

      Utilities typically take care of the large power projects of this nature. They make a budget estimate of the project cost and evaluate it against the revenue based on the kWh to be sold to the consumers. The projected cost will include the initial capital for the equipment, materials, and labor over the years of construction, cost of money and plant maintenances, and operation (see Section 1.4.2)

      The overall cost must include the transmission line from the power plant to the major switchyard. In case of a hydro project, the transmission lines are inevitably long and at higher transmission voltages. Diesel generation plants, on the other hand, are generally built for specific consumers in remote isolated areas. This may be a case of a mine up North needing 10–20 MW of power, for which the cost of building a transmission line would be rather prohibitive, in particular, if one evaluates it on the basis of the cost of km of line per MW delivered.

      It is not only the utilities that are involved with power generation. There are small power producers called Independent Power Producers (IPPs) for generating anywhere from 2 to 100 MW. They generally do not get involved with power distribution and readily sell all the power to the local utilities.

      The cost of fuel over the years of plant exploitation is always the most prevalent factor in the evaluation of a project development. This is where the hydro facility jumps ahead in spite of its huge cost of civil infrastructure. A gas fired plant will certainly be less costly on the basis of the initial cost of the plant and transmission line, but it is the cost of fuel per kWh produced that matters over the life of the plant. A diesel generation plant up North may be built at a low initial cost, but the cost of fuel is high, due to the additional cost of trucking and barging it to the site and storing it there for a full year. But do not forget that the usage of waste heat from the diesel engines can lift the plant efficiencies and reduce the cost of fuel usage.

      On the other hand, a fossil‐fuel operating plant costs a lot more to operate and is likely to be used for peaking duties in a daily cycle only. Therefore, the overall economics of building a fossil‐fuel operating plant in an area, which includes a mixture of different types of generation, must be estimated on the basis of its low operating hours.

      While the power plant projects are built with the highest quality of equipment and redundancy, intended for 40 years of operation, an industrial plant may be built for a shorter duration of, say 10 years.

      Levelized Cost Of Electricity (LCOE) is one of the yardsticks the owner's accountants use to compare the energy options for power plants. The formulae of totalizing the lifetime cost of production against the lifetime revenue are quite complex summations, using discount rates, inflation, and present worth accounting. Let the accountant work his figures. You as an engineer should understand the math behind it and offer technical options that may reduce the operating and initial costs to make the project more feasible.

      For instance, everything including a large hydro generation costs $0.04/kWh compared to an offshore wind farm priced at $0.19/kWh during the lifetime of the plant. The graph also shows the range of the cost for other alternatives. Clearly, the utility may have a hard time selling the wind power in this situation.

      (1.1)equation